Site hosted by Angelfire.com: Build your free website today!


Home Page   Work and Contact    June 24 to July 16   July 17 to July22.

July 23 to July29   July 30 to August 5   August 6 to August 12

  August 13 to August 19   August 20 to August 23   August 24

 

July 30th, Sunday

Another washout day.

July 31st, Monday

The rain had lessened, but there was still .a chance of showers at any time.  A second delivery of materials from Contractor's Warehouse arrived.  It is a shame that we can't get to use them.  The weather has delayed the pouring of the basement and garage floors.  The masons stopped by in the late morning and asked if we wanted to chance the pouring of the garage floor.  John needed something done.  They worked laying plastic, setting the wire and forms.  The concrete truck arrived and the process started.  There was a brief shower, just as they started.  Other than that time we lucked out with the rain.  The main mason and John finished up under the lights about 10:15PM.  What a long day!

It was good to see the supplies, but it is frustrating and discouraging not to be able to make any steady progress
A ray of hope!  If we could just get past the pouring of the two floors, at least we would be able to work on the framing.

 

August 1st, Tuesday

The same weather forecast.  The basement floor can't be poured until at least Wednesday.  John worked on the framing for the stairwell.  Mary Ann and John worked on repairing the fence and straightening the barn.  The evening was cool, so we cut and stacked 50 of the175 eighteen foot studs.  That way they will be ready when we get to that point.

 

August 2nd, Wednesday

No mason today!  What a disappointment!  Hopefully they will be here tomorrow.  John spent a good bit of time pre-cutting studs and door / window studs were assembled.

John cut more than 200 studs.  In the evening, he assembled all the door studs and many window studs.

 

August 3rd, Thursday

The morning started early, the first concrete truck was here before 8:00 AM. and two more were to follow.  This was the pivot point for moving on with the construction.  As evening approached, the threat of rain was an issue.  God was with us and the storms passed to our north and south.

It was exciting to see the floor actually being poured.  Marguerite, Alexandria, Dylan and Brett came over to watch for awhile.  Dylan was fascinated with the operation.  Alexandria watched with interest, but hated the sound of the concrete truck revolving the drum before the concrete was poured.
 
August 4th, Friday

The remaining floor joists were put in place and the the subfloor was started.  Laying the sheets and securing them with adhesive went quickly, but fastening them with screws was a tedious task.

This was a very annoying job  It is a great position to get the back of the neck burned.
 
August 5th, Saturday

It was an early start and Marguerite and Keith helped.  We worked the entire day and finished 99.9% of the subfloor.  There are four bump-outs that add to the complexity of the floor.  The only area that remains to be covered is a 3" by 25' at the end of the sunroom.  It was a satisfying, yet exhausting day

It was a great feeling to see the decking covering the floor joists.