Site hosted by Angelfire.com: Build your free website today!


Home Page   Work and Contact    June 24 to July 16   July 17 to July22.

July 23 to July29   July 30 to August 5   August 6 to August 12

  August 13 to August 19   August 20 to August 23   August 24

 

The work goes on...

July 17,  Monday

The masons have been working for two more days and the main wall is finished.  They are starting the ledge section.   John is getting the garage ready for the stone and the floor to be poured.  He set chunks of broken block and pieces of paper to fill the hollow cores of the blocks in the pit,

John feels like some progress is being make.

 

The masons are doing a fine job.

 

July 18, Tuesday

It is a gray day with light rain, but the masons are continuing to work.  In a way, it is a relief from the heat and humidity.  John had to make a run to Danville to get more of the buff mortar.  The progress is good.

July 19, Wednesday

There was a great deal of progress made today.  Much of the brick facing on the 18 inch exposure on the majority of the walls was done.
This the bay window area on the back of the master bedroom.

July 20, Thursday

This was a hallmark day.  Three thousand one hundred bricks later, the masons completed all the work.   Stone was ordered and three loads were delivered.  John and Mary Ann worked together to spread the fill into the garage.  Ingenuity was evident in the use of the truck's snow plow to move the mountains of stone.  The evening was spent fitting the treated sill.
Two masons are finishing up and one is cleaning the brick.
Up and over the mound of stone forcing it into the garage area around the pit.

July 21, Friday

It was an early morning start.  More sills were completed.  The remaining two loads of stone delivered.  We made steady progress.  At noon the fifty foot trailer arrived.  It backed up the driveway and dropped the  TJIs and  Parallams,  It was an awing sight seeing them rolled off the back of the trailer.  The afternoon we continued to work on the sill plates.  John was eager to get some of the main beams (Parallams).  The three beams in the sun room are in place by 9PM.  The sun is setting and the day is ending.

A quick drop rolled the entire stack of materials off the back of the truck.
July 22, Saturday

An other early start, we were out before sunrise, cutting and placing the Parallams.  The temperature was cool and the humidity was low.  As we were working, we noticed that some of the main beam materials were shorted in the order that was received yesterday.
These were all placed by Mary Ann and John working as a team.