Site hosted by Angelfire.com: Build your free website today!

Petőfi Bridge

Location and name of the bridge
Name of the bridge: "Petőfi" bridge
Distance: 1644+300 km
Country: Hungary
City/town: Budapest
Year of building - completion: 1933 - 1937.
Year of rebuilding - completion: 1945 - 1952.
renewal: 1978 - 1979.
Span lengths: 29.28 + 29.11 + 29.05 + 112.0 + 154.0 + 112.0 + 33.06 m
Roadway widths: 2.1 + 0.5 + 20.40 + 0.5 + 2.1 m
Designer: UVATERV
Main contractor: MÁVAG

Traffic function of the bridge
highway bridge (4 lanes) with tramway (2 tracks)

Antecedents; the history of the bridge
The building of this new bridge and to name it after the Hungarian governor, Miklós Horthy, was ordered by law No. XI. in 1930. Ten designer teams prepared 17 plans, and all of the prize winner ones were made by Hungarians. The first prize winner plan was a chain bridge of János Kossalka and Gyula Wilder, the second one was the arch bridge of Győző Mihailich and Iván Kotsis, while the third one was an other arch solution of Jenő Kiss and Pál Sávoly. Győző Mihailich presented an other plan containing a single span cable bridge version.
It can be seen, that those designs, which were preferred by the jury, and all of the other ones, too, gave such solutions, in which the top of the main girders was much over the floor system. Its main reason can be found among the design conditions, as taking into account the prescribed height alignment of the floor system, an alternate variation could not be solved.
Later the design conditions in this sense were changed and a new design was carried out by the Bridge Department of the Ministry, and finally that version was accepted and realized. The design process was directed by Pál Álgyai-Hubert.
The bridge had four main girders with strong cross bracings and both upper and lower wind bracings.
The bridge was blown up in January 1945. The main part of the original structure could be used during rebuilding.
In 1978-79 the floor structure had to be replaced and at that time the five-span old steel structure on Pest side was demolished and a new, three span reinforced concrete structure made from prefabricated beams was built.

The technical data of the bridge

Structural system, span lengths, widths
The main girder of the bridge over the river is a three span continuous deck-type truss of changing height.

Deck
The complete deck was replaced in two phases, one half of the bridge width could be used all time. The old reinforced concrete slab had no water protection and it was seriously damaged. The formwork of the new reinforced concrete slab was made from steel corrugated sheets of 3 mm thick and it was connected by welding to the other structural elements. The thickness of the concrete slab is 15 cm.

Foundation, substructure
Original foundations of the abutments were reinforced concrete caissons, while those of the river piers were steel caissons. They had a concrete core covered with limestone blocks.

Quantities of applied materials
Weight of steel construction: 7500 t

Method of construction/erection; joints
During the rebuilding the side spans were divided by intermediate temporary supports, while the middle span was erected as free cantilevers from both sides.

Test loading(s), periodical assessment of serviceability
After the reconstruction of the bridge in 1980 it was detected that the expansion joints on the pier on the Buda side got stuck in under all the four main girders and operated as fixed supports. Therefore it was decided to modify them in a way that the rollers should be replaced by sliding-tilting bearing with complete teflon coating manufactured by the Maurer firm. For accurate position of the sliding surfaces the bridge had to be raised and after the removal of the rollers the new bearings had to be inserted.
It was also noted that two intermediate piers of the bridge are moving in the axial direction. To get information about the behaviour of the bridge a computer simulation check was carried out to determine the effect of the vehicle loading, the temperature changes, etc. in this respect. The results showed that the present state is not dangerous, but the complete repair of bearings is necessary as soon as possible.

Literature
Haraszti, G.: A Boráros-téri Petőfi Duna-hid ujjáépitése, MÉLYÉPTERV Műszaki Közlemények, 1953. No. 9.
Bácskai, E. - Kozma, K.: A Petőfi-hid felujitása, Mélyépitéstudományi Szemle 1980. No.3.

Links to drawings:

gif 1 gif 2

Link to the next page:

Liberty Bridge

back to homepage