BUDGET FOR PRELIMINARY PROJECT COST ESTIMATION
SAKYA CHUDUE CHOEKOR NORLING MONASTERY
1: Project : BLOCK B
2: Preliminary Project Cost Estimation : In Indian Rupees 36,77,330.00
3: Owner : SAKYA CHUDUE CHOEKOR NORLING MONASTERY
|
S.No.
|
Description |
Amt. Ind. Rs.
|
|
1
|
Civil Work 5548 Sqft. @Rs.800 |
23,58,400.00
|
|
2
|
Internal and external plumbing including overhand tanks @10% of Civil Cost. |
2,35,840.00
|
|
3
|
Internal land external electrificaiton @10% OF Civil cost |
2,35,840.00
|
|
4
|
Land development, roads, storm water drains, yard lighting, landscaping, paving, walkways etc.@15% |
3,53,760.00
|
|
5
|
Compound wal and gates |
Nil
|
| TOTAL Building Cost |
31,83,840.00
|
|
|
6
|
Add Architecht & Engineer's fees @5% of the Total cost spread Over the period of construction for 12 month. |
1,59,190.00
|
| TOTAL |
33,43,030.00
|
|
| Contingencies @ 10% |
3,34,300.00
|
| Grand TOTAL Ind Rs. |
36,77,330.00
|
|
| US $ + Ind. Rs. 47.00 |
$78,241.00
|
Dated : 06 June, 2002
Prepared By: Dorjee Builders,
Dharasmala
Copyright© Sakya Chudoe Choekor Norling Monastery Charitable Trust, Dharamsala