Site hosted by Angelfire.com: Build your free website today!

BUDGET FOR PRELIMINARY PROJECT COST ESTIMATION

SAKYA CHUDUE CHOEKOR NORLING MONASTERY

Back to Budget

1: Project : BLOCK B

2: Preliminary Project Cost Estimation : In Indian Rupees 36,77,330.00

3: Owner : SAKYA CHUDUE CHOEKOR NORLING MONASTERY

S.No.
Description
Amt. Ind. Rs.
1
Civil Work 5548 Sqft. @Rs.800
23,58,400.00
2
Internal and external plumbing including overhand tanks @10% of Civil Cost.
2,35,840.00
3
Internal land external electrificaiton @10% OF Civil cost
2,35,840.00
4
Land development, roads, storm water drains, yard lighting, landscaping, paving, walkways etc.@15%
3,53,760.00
5
Compound wal and gates
Nil
  TOTAL Building Cost
31,83,840.00
6
Add Architecht & Engineer's fees @5% of the Total cost spread Over the period of construction for 12 month.
1,59,190.00
  TOTAL
33,43,030.00
  Contingencies @ 10%
3,34,300.00
  Grand TOTAL Ind Rs.
36,77,330.00
  US $ + Ind. Rs. 47.00
$78,241.00

Dated : 06 June, 2002

Prepared By: Dorjee Builders,

Dharasmala

Copyright© Sakya Chudoe Choekor Norling Monastery Charitable Trust, Dharamsala