YEAR 2001
IMPROVEMENTS
This budget plan, if
followed for the entire five years, anticipates devoting $250,000 to overlaying
projects and drainage work. Since it is more expensive to do $50,000 dollar
projects than $100,000 projects because of staging costs to contractors, I would anticipate
doing a paving project in the second year of the five year plan and a second
project in the fourth or fifth year of our plan. The affected areas would be
Indian Springs road, Crossroads Drive, and Deer Lake Trail from the water tower
towards the POA business office. These roads are already experiencing stressing
in many areas and in some cases failure of the surface
area.
YR
-2001
In 2001, maintenance crews
will improve landscaping and drainage in these affected areas to relieve damage
to the roadway, to facilitate mowing (lessening damage to equipment due to rough
terrain) and to improve appearance by removing additional stumps and dirt work
as well as the same work on Flint Ridge Drive from our cabins to the water
tower, with other areas receiving the same attention of a time and priority
basis for the duration of the five year plan.
In 2001, we hope to obtain
generators for the booster pump on Crossroads Drive (serving Indian Springs),
for the water plant, and for RV1. We did not have sufficient funds available to
dedicate for these purposes, but I hope to find serviceable generations at
bargain prices and to acquire them out of existing water department
funds.
YRS-2001-2005 Further in five year plan,
we hope and plan to obtain a $4,000,000 grant/loan (75% grant/25% low interest loan) which
will be used to build a water tower to serve the Indian Springs area, move the
booster station back close to the water tower which will serve all areas,
including block 3 that are north and west of the water tower, install two
additional pressure reducing stations so that we can utilized the top 1/3 of our water tower that
we are not presently using for additional water storage and pressure, increase
the capacity of the water plant from a 375,000 gallon per day plant to a
1,000,000 gallon per day plant, extend a water line to RV1 (on which we are now
on a consent order from DEQ to do), and to extend other lines, or replace aging
lines and thereby to obtain additional customers.
The application process
through construction takes appx. two years, our engineering report that has to
accompany the application will be available for the boards approval, at our
November meeting, and with the boards approval, application will immediately be
made for the Rural Development funds. Actually construction would begin then in
year two or three of the five year plan, depending on the actual duration of the
application process (as you know the federal government seldom works
fast).
YR 2001~ Fix up, paint up on the White House. Admin
Building, Deer Lake Clubhouse, Round House, and other common building as funds
are available
YR 2001 -
Re-institute flat bottom boat
service on our two lakes similar to our
canoe service (boats on trailer,
and dropped off on location, rather than left there as to negate vandalism
and
abuse as we have had this year and the
past).
YR 2001 -
Employ at least on a part-time
basis, a groundskeeper for the common facilities around the admin office area,
cabins, white house, etc., to improve the appearance and facilitate improved
maintenance.
YR 2001 -
Acquisition of the previously
outlined equipment (mower, etc.).
YR 2001 -
Installation of new guard shack
on Construction Gate entrance.
YR 2001 -
Acquisition of a roller and
water truck to be able to maintain roads better.
YR2001 -
Better training for maintenance
and water crews to improve work product
YR2001 -
Begin maintenance on areas that
have not had maintenance in years.
YR2001 -
Institution of other revenue
sources acquisition that will lessen dependence on POA
dues.
YR2001 -
Repair of steps and hand rail at
Clear Lake.
YR2001 -
Increased prosecution on
delinquent account holders.
YR2001 -
Improvements in building and
subdivision code enforcement.
YR2001 -
Improvements in Administration
software to facilitate better efficiency in billing and other internal
operations.
YR2001 -
Improvements in financial
reports to board members and POA members.
YR2001 -
Trimming all overhanging
branches from roadways
YR2001 -
Removal of two trees from
baseball field and general improvements to it.
YR2001 -
Reroof RVl clubhouse and repair
of out front lighting
YR2001 -
Septic System R & R at
RV2