Progress Report

For

Sony Projection Television Model 60XBR500

 

New Model Evaluation Team

Task Progress Report

1. Task Number (Include Project Revision Number):

                                                                                      10-11-12-13-15-16-17-21-22-34

2. Task Name:

                       New Model Evaluation

3. Today’s Date:

                          March 09, 2003

3a. Date you started this task:

                           March 09, 2003

4. Resource Name: 

                              Quality Control                                                                                      

4a. ID Number:

                      10-11-12-13-15-16-17-21-22- 34                   

5. Resource Group:

                              Quality Control New Model Evaluation Team

6. Please Enter Hours Worked Per Day

Sun

Mon

Tue

Wed

Thr

Fri

Sat

Total

H: Holiday V: Vacation

N: Not scheduled to work

N/A

   8

   8

   8

   8

   8

  8

   48

 

7. Do you consider this task to be   8. On                  9. Behind                    10. Ahead of

If Behind or Ahead,                          Schedule            Schedule                     Schedule

Approximately how long:

11. What tasks are affected if this task is either ahead or behind =>

 21

 22

 23

 

 

 

 

 

 

 

 

 

12. Briefly Describe Progress for this task

     

       On Schedule

13. Briefly Describe any Problems you encountered

 

      Task #10 required Saturday overtime to complete

       The Finished Goods Inspection.

14. Briefly Describe Resolutions to Problems

 

                Scheduled overtime to

                Complete Task #10.

15. Are there any other concerns

 

 

                None at this time

16. Other Comments / Concerns

 

                                                    Special tests are on schedule, and continuing with the 600 hr. aging.