PROGRESS OF UPPER KRISHNA PROJECT
AS AT 31st MARCH 1999
PROGRAM |
PROGRESS |
|
NARAYANPUR DAM AND ALLIED WORKS |
COMPLETED |
|
ALMATTI DAM AND ALLIED WORKS |
||
| LEFT BANK EARTH AND MASONRY DAM | EL 528.800 m |
EL 528.756 m (Avg) |
| SPILL WAY | EL 509.016 m |
THE SPILLWAY INCLUDING BRIDGE HAS BEEN COMPLETED |
| RIGHT BANK MASONRY DAM POWER DAM | EL 528.760 m |
EL 528.756 m (Avg) |
| NON OVER FLOW SECTION | EL 528.760 m |
COMPLETED TO TOP OF DAM EL 528.76m |
NARAYANPUR LEFT BANK CANAL |
||
MAIN CANAL |
||
LENGTH |
78 KM |
78 KM |
IRRIGATION AREA |
47233 ha |
50017 ha |
| SHAHPUR BRANCH CANAL | ||
LENGTH |
76 KM |
76 KM |
IRRIGATION AREA |
122120 ha |
107928 ha |
MUDBAL BRANCH CANAL |
||
LENGTH |
50.8 KM |
Works in Km 0 to 50.8 including all distributaries(except lining for some reaches of distry 18) and laterals completed. |
IRRIGATION AREA |
51000 ha |
44,015 ha |
| INDI BRANCH CANAL | ||
LENGTH |
175 Km |
Indi Branch Canal from Km 0 to 64 has been completed in all respects and water has been let into the canal upto field outlets,Works in the reach from KM 65 to 150 are in progress.Earthwork to an extent of 98.34 % is completed in the reach from km 65 to 120 and to an extent of 92.34% in the reach from km 121 to 150.Works are in progress from KM 151 to 157.Earthwork to an extent of 50 % is completed in the reach from Km 158 to172 .Works in Km 158 to 164 and 166 are in progress.The balance works in Km 158 to 161,165,167 to 172 are awarded.Out of 132 CD works in reach Km 65 to 150 ,65 are completed and 40 are in progress. |
IRRIGATION AREA |
131260 ha |
64,047 ha |
| JEWARGI BRANCH CANAL | ||
LENGTH |
85.26 Km |
Works in Km 0 to 86 are in progress.Earthwork completed:95 % in Kms 0 to 50, 88 % in Kms 51 to 70. & 36 % in Km 71 to 86 .Out of 164 CD works in reach from 0 to 86 Km,94 are completed and 37 are in progress. |
IRRIGATION AREA |
57100 ha |
1595 ha |
| NARAYANPUR RIGHT BANK CANAL | ||
LENGTH |
95 KM |
Work in Km 0 to 85 (except in forest land ) are in progress. Earth Work completed : 97% in Km 0 to 70 (except forest land ) 75% in Km 71 to 78 & 60 % in Km 79 to 85. Out of 156 CD works in reach from 0 to 85 Km,103 are completed and 24 are in progress. |
IRRIGATION AREA |
84,000 ha |
951 ha |
| ALMATTI LEFT BANK CANAL | ||
LENGTH |
103.00 KM | Head work of ALBC Lift Irrigation scheme is raised to RL 524.00m.Excavation of intake channel completed.Earthwork in Km 0-9 completed.Earthwork and CD works from KM no 13 to 27 are in progress.Km 19 & 22 completed.Work has started in Km 28,29 & 30.Out of 62 CD Works in reach Km 1 to 27, 40 are completed and 22 are in progress |
IRRIGATION AREA |
20,235 ha | - |
| ALMATTI RIGHT BANK CANAL | ||
LENGTH |
121 KM | Head work and intake structures are in progress.Intake structure is brought to RL 516.00 m Bed lining and side lining of intake channel is completed to a length of 60 m.Delivery chamber is completed. |
IRRIGATION AREA |
16,100 ha | |
| MULWAD LIFT IRRIGATION SCHEME | ||
LENGTH |
128.50 KM | Excavation of intake Channel is completed.Construction of delivery chamber completed Side retaining walls raised to RL 521.70m.Backfill (earthwork) raised to RL 516.50m(Avg).Jackwell structure is raised upto RL 508.75m in all respects |
IRRIGATION AREA |
30,850 ha | - |
| RAMPUR LIFT IRRIGATION SCHEME | ||
LENGTH, |
37.50 KM | Head work for Stage - I in progress.Intake channel completed. Out of 14 km length Lead-off Channel, 13 Km work is in progress Km 6 is under finalisation of tender. |
IRRIGATION AREA |
20,235 ha | |
| INDI LIFT IRRIGATION SCHEME | - |
|
LENGTH |
96.50 KM | Estimates and draft tender schedules of intake structures,intake chanel are cleared by the Technical Sub Committee subject to some observations.Estimates of Lift scheme canal from Km 1 to 11 are under preparation.For balance length from Km 12 to 96.50 survey work is in progress |
IRRIGATION AREA |
41,900 ha |
|
| NOTE: 1 In general the progress in project implementation is satisfactory.It is expected that the project will be completed by the year 2000. 2. In regard to Y2K preparedness: (i)The company has taken care of Y2K compliance for internal operations.(ii)We have obtained certificates from our Transfer Agents,M/S Kirloskar Computer Services Ltd- stating that they have taken necessary steps for the year 2000 compliance to ensure that the reports that are processed and released by them in respect of bonds held by our bondholders are in order and M/s Karvy Consultants Ltd -they have complied with Y2K requirements and necessary updationto the software at their end has also been completed |
||