PROGRESS OF UPPER KRISHNA PROJECT

AS AT 31st MARCH 1999

PROGRAM

PROGRESS

NARAYANPUR DAM AND ALLIED WORKS

COMPLETED

ALMATTI DAM AND ALLIED WORKS

LEFT BANK EARTH AND MASONRY DAM

EL 528.800 m

EL 528.756 m (Avg)

SPILL WAY

EL 509.016 m

THE SPILLWAY INCLUDING BRIDGE HAS BEEN COMPLETED

RIGHT BANK MASONRY DAM POWER DAM

EL 528.760 m

EL 528.756 m (Avg)

NON OVER FLOW SECTION

EL 528.760 m

COMPLETED TO TOP OF DAM EL 528.76m

NARAYANPUR LEFT BANK CANAL

MAIN CANAL

LENGTH

78 KM

78 KM

IRRIGATION AREA

47233 ha

50017 ha

SHAHPUR BRANCH CANAL

LENGTH

76 KM

76 KM

IRRIGATION AREA

122120 ha

107928 ha

MUDBAL BRANCH CANAL

LENGTH

50.8 KM

Works in Km 0 to 50.8 including all distributaries(except lining for some reaches of distry 18) and laterals completed.

IRRIGATION AREA

51000 ha

44,015 ha

INDI BRANCH CANAL

LENGTH

175 Km

Indi Branch Canal from Km 0 to 64 has been completed in all respects and water has been let into the canal upto field outlets,Works in the reach from KM 65 to 150 are in progress.Earthwork to an extent of 98.34 % is completed in the reach from km 65 to 120 and to an extent of 92.34% in the reach from km 121 to 150.Works are in progress from KM 151 to 157.Earthwork to an extent of 50 % is completed in the reach from Km 158 to172 .Works in Km 158 to 164   and 166 are in progress.The balance works in Km 158 to 161,165,167 to 172 are awarded.Out of 132 CD works in reach Km 65 to 150 ,65 are completed and 40 are in progress.

IRRIGATION AREA

131260 ha

64,047 ha

JEWARGI BRANCH CANAL

LENGTH

85.26 Km

Works in Km 0 to 86 are in progress.Earthwork completed:95 % in Kms 0 to 50, 88 % in  Kms 51 to 70. & 36 % in Km 71 to 86 .Out of 164 CD works in reach from 0 to 86 Km,94 are completed and 37 are in progress.

IRRIGATION AREA

57100 ha

1595 ha

NARAYANPUR RIGHT BANK CANAL

LENGTH

95 KM

Work in Km 0 to 85 (except in forest land ) are in progress. Earth Work completed : 97% in Km 0 to 70 (except forest land ) 75% in Km 71 to 78 & 60 %  in Km 79 to 85.    Out of 156 CD works in reach from 0 to 85 Km,103 are completed and 24 are in progress.

IRRIGATION AREA

84,000 ha

951 ha

ALMATTI LEFT BANK CANAL

LENGTH

103.00 KM Head work of ALBC Lift Irrigation scheme is raised to RL 524.00m.Excavation of intake channel completed.Earthwork in Km 0-9 completed.Earthwork and CD works from KM no 13 to 27 are in progress.Km 19 & 22 completed.Work has started in Km 28,29 & 30.Out of 62 CD Works in reach Km 1 to 27, 40 are completed and 22 are in progress

IRRIGATION AREA

20,235 ha

-

ALMATTI RIGHT BANK CANAL

LENGTH

121 KM Head work and intake structures are in progress.Intake structure is brought to RL 516.00 m Bed lining and side lining of intake channel is completed to a length of 60 m.Delivery chamber is completed.

IRRIGATION AREA

16,100 ha
MULWAD LIFT IRRIGATION SCHEME

LENGTH

128.50 KM Excavation of intake Channel is completed.Construction of delivery chamber completed Side retaining walls raised to RL 521.70m.Backfill (earthwork) raised to RL 516.50m(Avg).Jackwell structure is raised upto RL 508.75m in all respects

IRRIGATION AREA

30,850 ha

-

RAMPUR LIFT IRRIGATION SCHEME

LENGTH,

37.50 KM Head work for Stage - I in progress.Intake channel completed. Out of 14 km length Lead-off Channel, 13 Km work is in progress Km 6 is under finalisation of tender.

IRRIGATION AREA

20,235 ha
INDI LIFT IRRIGATION SCHEME

-

LENGTH

96.50 KM Estimates and draft tender schedules of intake structures,intake chanel are cleared by the Technical Sub Committee subject to some observations.Estimates of Lift scheme canal from Km 1 to 11 are under preparation.For balance length from Km 12 to 96.50 survey work is in progress

IRRIGATION AREA

41,900 ha

NOTE:

1 In general the progress in project implementation is satisfactory.It is expected that the project will be completed by the year 2000.

2. In regard to Y2K preparedness: (i)The company has taken care of Y2K compliance for internal operations.(ii)We have obtained certificates from our Transfer Agents,M/S Kirloskar Computer Services Ltd- stating that they have taken necessary steps for the year 2000 compliance to ensure that the reports that are processed and released by them in respect of bonds held by our bondholders are in order and M/s Karvy Consultants Ltd -they have complied with Y2K requirements and necessary updationto the software at their end has also been completed