Progress for Project |
May |
23 - Discussion
with Sunny with regards to the Programming language use. Change from
Java to VB.NET |
26 - Creating and
coding of the program, defining of algorithm by mohan. 27 - Draft of 3 web pages- Login in, Reading
from log was created.
29 - hyperlink the pages.
30 - Generating the data and storing them in the ODBC
|
June |
01 to 02 - Obtain
the Log Event from NYP, link
the ODBC to the program Discussion with Sunny about the progress of
the Project- by Mohan
|
04 - 06 Trial of
Prototype |
07 - Refining the
Prototype |
|
|
|
|
|
This Week (2/6/03 - 07/06/03)
- Link the ODBC the program
- Running the program
- Debugging
Next Week (9/6/03 - 11/6/03)
- Final Debugging of prototype
- Submitting of Project
- Presentation
|