ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
1 | Emirates Post Datawarehouse Project | 26 days | Sat Jan 10, '04 | Tue Feb 10, '04 | | 0% |
2 | Client readiness | 0 days | Sat Jan 10, '04 | Sat Jan 10, '04 | | 0% |
3 | Project Startup | 0 days | Sat Jan 10, '04 | Sat Jan 10, '04 | | 0% |
4 | Busines Analysis / Strategy | 3 days | Sat Jan 10, '04 | Mon Jan 12, '04 | | 0% |
5 | Identify Business requirements | 2 days | Sat Jan 10, '04 | Sun Jan 11, '04 | | 0% |
6 | Define Objectives and Purpose of the Datawarehouse | 1 day | Mon Jan 12, '04 | Mon Jan 12, '04 | | 0% |
7 | Information Analysis | 6 days | Mon Jan 12, '04 | Mon Jan 19, '04 | | 0% |
8 | Information requirement definition | 1 day | Mon Jan 12, '04 | Mon Jan 12, '04 | | 0% |
9 | Requirement Specification Document | 3 days | Tue Jan 13, '04 | Sat Jan 17, '04 | | 0% |
10 | Requirement Specification Document Sign off | 2 days | Sat Jan 17, '04 | Mon Jan 19, '04 | | 0% |
11 | Oracle Product Deployment | 4 days | Sat Jan 10, '04 | Tue Jan 13, '04 | | 0% |
12 | Oracle 9iAS installation | 3 days | Sat Jan 10, '04 | Mon Jan 12, '04 | | 0% |
13 | Oracle 9i Database Installation | 4 days | Sat Jan 10, '04 | Tue Jan 13, '04 | | 0% |
14 | Design | 7 days | Tue Jan 13, '04 | Wed Jan 21, '04 | | 0% |
15 | Data Model | 7 days | Tue Jan 13, '04 | Wed Jan 21, '04 | | 0% |
16 | Staging Area Data Model Design | 2 days | Tue Jan 13, '04 | Wed Jan 14, '04 | | 0% |
17 | Datawarehouse Data Model Design | 3 days | Thu Jan 15, '04 | Mon Jan 19, '04 | | 0% |
18 | Data Model Design Signoff | 2 days | Mon Jan 19, '04 | Wed Jan 21, '04 | | 0% |
19 | Development & Test | 21 days | Thu Jan 15, '04 | Tue Feb 10, '04 | | 0% |
20 | Source to Staging | 9 days | Thu Jan 15, '04 | Mon Jan 26, '04 | | 0% |
21 | Define Staging Area metadata | 1.5 days | Thu Jan 15, '04 | Sat Jan 17, '04 | | 0% |
22 | Map Source to Staging | 2 days | Sat Jan 17, '04 | Mon Jan 19, '04 | | 0% |
23 | Deploy Database Objects | 2 days | Mon Jan 19, '04 | Wed Jan 21, '04 | | 0% |
24 | Deploy Mappings | 1.5 days | Wed Jan 21, '04 | Sat Jan 24, '04 | | 0% |
25 | Schedule / Execute / Test Mappings | 2 days | Sat Jan 24, '04 | Mon Jan 26, '04 | | 0% |
26 | Staging to Warehouse | 11 days | Mon Jan 26, '04 | Mon Feb 9, '04 | | 0% |
27 | Define Warehouse Metadata | 1.5 days | Mon Jan 26, '04 | Wed Jan 28, '04 | | 0% |
28 | Map Staging to Warehouse | 2 days | Wed Jan 28, '04 | Sat Jan 31, '04 | | 0% |
29 | Deploy Database Objects | 2 days | Sat Jan 31, '04 | Mon Feb 2, '04 | | 0% |
30 | Deploy Mappings | 1.5 days | Mon Feb 2, '04 | Wed Feb 4, '04 | | 0% |
31 | Schedule / Execute / Test Mappings | 2 days | Wed Feb 4, '04 | Sat Feb 7, '04 | | 0% |
32 | Development Signoff | 2 days | Sat Feb 7, '04 | Mon Feb 9, '04 | | 0% |
33 | Data Loading | 5 days | Wed Feb 4, '04 | Tue Feb 10, '04 | | 0% |
34 | Schedule Data Load from Source to Staging | 1 day | Wed Feb 4, '04 | Thu Feb 5, '04 | | 0% |
35 | Data Loading Process | 1 day | Thu Feb 5, '04 | Sat Feb 7, '04 | | 0% |
36 | Generation of Error Records | 1 day | Sat Feb 7, '04 | Sun Feb 8, '04 | | 0% |
37 | Schedule Data Load from Staging to Warehouse | 1 day | Sat Feb 7, '04 | Sun Feb 8, '04 | | 0% |
38 | Data Loading Process | 1 day | Sun Feb 8, '04 | Mon Feb 9, '04 | | 0% |
39 | Generation of Error Records | 1 day | Mon Feb 9, '04 | Tue Feb 10, '04 | | 0% |
40 | Signoff on Data Load | 2 days | Sun Feb 8, '04 | Tue Feb 10, '04 | | 0% |
41 | End User Application Build | 10 days | Sat Jan 31, '04 | Wed Feb 11, '04 | | 0% |
|