Elkhart House Project - 

August 18, 2001

It was siding weekend.  We got all the siding up on the south wall and half the siding on the back wall.  We also put the 4x8 sheets under the porch to cover it up.  I installed the kitchen window and reran the second floor main drain (it had to be twisted a bit).  We also took some time to do some farm work.  It rained quite a bit on Thursday (Aug. 16) and it rained on on Saturday (August 18).  Just a slow steady rain for an hour or more.  The 30# felt kept the house dry.

 

I wish I would have got the dormers done.
A look at the porch and front/side walls.
The inside is getting dark with the outside walls covered.
Here is a different look.  Up the hill from across the street.  We're standing about 1/4 mile of more down the hill below the house.