Oil and Gas, Petrochemical Experience:
(OGP1, OGP2, OGP3, OGP4, OGP5 and OGP6)
OGP1: Proposal and Final Design (Maintain Potential
Projects) with ABB Lummus Alireza Limited
Company.
Mr. Garin, is responsible in the supervision of the daily work and
activity of senior engineers, engineers and designers assigned to the
discipline. Prepares a written report including work items accomplished
since the last review meeting, areas of concern and forecast of work to
be accomplished during the next week; Prepares the Matrix for comments
and stating the disposition of each comment.
Mr. Garin also perform Mechanical Engineering Calculations,
Development of the Mechanical Equipment Specifications and Budgetary
costs as well as the Technical Bid Evaluation for the following
facilities indicated below.
Abu Safah AM (Arab Medium) Producing Facilities:
To meet the objectives of the 2002-2011 Abu Safah Crude
Program, new Offshore Crude Gathering Facilities and Onshore Crude
Processing
Facilities are required to be engineered and built to increase
Arabian Medium crude production.
Offshore Crude Gathering Facilities:
- Subsea Production Systems, Electric Submersible Pumps - ESP's,
Scraping Facilites, Slops Collection Tank System, Washdown System
including Pump, Demulsifier injection skid with sufficient storage and
metering pumps, Overhead Bridge Crane, Pedestal Crane, Jib Crane, and
Electric Driven Monorail Hoist.
Onshore Crude Processing Facilities:
- Two parallel horizontal split flow, three phase Low Pressure
Production Trap (LPPT) and equipped with Three 50% capacity LPPT Water
Draw-Off Pumps.
- Crude Heating System consisting of First Stage DRY/WET Heat
Exchangers and Second Stage Crude Trim Heat Exchangers.
- Two Spheroid of three phase type and equipped with three 50 %
capacity Water Draw-Off Pumps.
- Single Train of three stage Wet Crude Handling (WCH)
Facilities.
- Stabilization Facilites with two independent stabilization trains
consisting of 12.5 foot stabilization column with three 50% capacity
stabilizer bottoms pump on each stabilizer columns with two 100% thermo-
siphon steam heated reboilers and with an upstream 20 MBBL spheroid
with three 50% Spheroid bottom pumps and downstream Stabilized Crude
Coolers (Fin Fan Coolers) capable of cooling 300 MBCD (316 MBOD) of Abu
Safah AM crude from 190 degree F to 150 degree F during summer
conditions.
Safaniya Trunkline 4 (TL-4) Pipeline.
- Scraper Receivers and Launchers, Chemical Injection Skid, and Jib
Crane.
Marjan Offshore Facilities Upgrade Project.
Mr. Garin conducted a site surveys to existing Marjan facilites to
verify
the necessary information for upgrade and tie-in details.
- Replacement of four submersible pumps with four new submersilbe
pumps and one vertical line shaft.
- Conversion of the existing R-12 based Refrigeration system to
R134A- based system.
- Replacement of two heat exchanger serving the gas refrigeration
system.
OGP2: Project undertaken with PT Gema SemBrown.
Condensate Stabilization Plant.
Managed and directed the activities of a multidiscipline
engineering
team through project development, detailed design and
construction.
Developed an authority / responsibility check list to facilitate
and keep
track of team members. Coordinated overall engineering activities
including development of design concepts, scope, and details as
leader of
the project engineering team. Communicated project details
between all
members of the interdisciplinary team as required to assure
continuity of
design and construction. Reviewed and approved work of discipline
engineers, and recommended enhancements to systems for improved
operability, efficiency and capital cost. Developed and
maintained
schedules for utilization of engineering team, and ensure
completion of
all engineering deliverables as scheduled. Developed management
plan for
the supervision of contractors and tender / bid / contract award
processes
on behalf of clients. Produced concise periodic reports to
communicate
project progress and significant issues to project management,
corporate
line management and to client project management team.
OGP3: Projects undertaken with Technip Geoproduction Sdn.
Bhd.
Provide system level technical expertise in the design of a
system in
order to sustain and/or improve system performance, reliability
and
safety. Manage resolution of technical issues, including
developing
project scope, schedule and cost. Perform and check engineering
calculations, technical specifications and material
requisitions. Provides
technical evaluation of bid proposals and make recommendations.
Interface
with client, project management team, insurance underwriter
representative. Reads technical material to enhance skills and
knowledge
and maintain an understanding of current industry
standards.
Condensate Stabilization Plant, Bintulo Crude Oil Terminal,
and
Polyethylene Plant.
Responsible in the detailed engineering design of HVAC System
and Fire
Protection System for Blast Proof Control Building. The HVAC
system
apply's three modes of operation, that is Pressurisation,
Depressurisation
and Purging. Also responsible in the hydraulic calculations
(steady state
and transient analysis) and system design of the Fire Fighting
System. The
fire fighting covers Central Fire Water Pumping Facilities, Fire
Water
Distribution (Compounded Loops or Network or Fire Water Ring
Mains)
Systems, Hydrants, Deluge System and Passive System for Exposure
Protection, Hose Reel Systems, Dry and Wet Automatic Sprinklers,
Fixed
Foam Systems including Foam Generators, Carbon Dioxide
Systems.
OGP4: Projects undertaken with Sime Engineering Sdn. Bhd.
Generally performs work which involves the preparation,
interpretation
and review of calculations, technical specifications, system or
equipment
with relatively complex features. Reviews design drawings for
completeness
and constructibility. Prepares reports and summaries documenting
the
mechanical engineering activities. Assist in developing and
implementing
proposals. Communicate goals, scope, approach and schedules to
mechanical
team to assure the attainment of the goals set forth by the
management.
Floating Production, Storage and Off-loading (FPSO) System
and Subsea
System.
- Performed preliminary engineering for the FPSO and Subsea
system in
support of bids by Sime Engineering and Aker Engineering. The
FPSO is a
modified crude oil-carrying tanker which has an accommodation
for a
total of 60 persons although the normal operations crew is 38
persons.
- Supervised the joint venture mechanical group in preparing
the
preliminary sizing and layout of the following: Topside
production
systems and equipment and Subsea Chemical Injection System.
- On safety side was responsible for the preliminary
identification
and layout of the following: escape tunnel on the vessel's
port side; an
open escape route on the starboard side, plus two escape
routes from all
equipment units. The escape tunnel's do have a pressurised
interior and
fire-protected exterior.
MLNG DUA Onshore Project and EPMI Seligi-C Offshore Platform
Project.
HVAC System (Onshore/Offshore).
- Responsible in the detailed engineering design of HVAC
Systems with
three modes of operation: Pressurisation, Depressurisation and
Purging.
The HVAC System are specifically designed for Offshore
Platform Control
Rooms and Living Quarters; Onshore Blast Proof Essential
Buildings that
is Control Rooms, Analyzer House, Field Auxiliary Building;
Onshore
Sub-Station non blast proof building.
- Prepared for the aboved specialized HVAC Systems the Cause
and
Effect Matrices (such as sequence table) and Emergency
Shutdown Matrices
(for safeguarding systems) and Procedures.
OGP5: Projects undertaken with Fluor Daniel Arabia
Limited.
In a lead capacity, Mr. Garin's is responsible for mechanical
engineering necessary to complete projects and ensuring quality
standards
/ISO requirements are adhered to at all stages of the design
process. Mr.
Garin's accountability also includes the following: Define and
develop the
Mechanical Scope of Work, Design Basis Document, Design Report or
Technical Report; Supervises the daily work and activity of
senior
engineers and designers assigned to the discipline; Review and
approved
key design documents including drawings, calculations, technical
specifications, material requisitions, bid evaluations and award
recommendations; Prepares Mechanical Punch Lists, reports and
summaries
documenting the engineering discipline's activities;
Participates in
design reviews during all phases of project and discussions with
other
disciplines and the client. Produced concise periodic reports to
communicate project progress and significant issues to project
management
and to client project management team.
Marjan Completion.
This Project provides for the Demothball, Completion and
Commissioning
of Marjan Oil and Gas Gathering Facilities.
- Have done a detailed field survey worked of facilities and
was able
to determine current "as built" status and assessed the degree
of
completion of three facilities, and their general condition.
- Engineered and prepared the quotation requests for the
following
mechanical equipment's such as: Fin Fan Coolers, Plate Heat
Exchanger;
Centrifugal Air Compressors, ASME Heatless Air Driers;
Hypochlorite
Generator; Refurbishment and Start Up Spare Parts of Rotating
Equipments.
- Reviewed and modified the Air Conditioning Systems
Engineering
Design of Process Management Center, Process Interface and
Switchgear
Buildings, to ensure adequacy of design and to meet the
current ARAMCO
engineering standards.
Wet Crude Handling Facilities.
- Responsible in the engineering design of mechanical
equipment's
consisting of Low Pressure Tanks such as Sphere and Spheroid,
Atmospheric Wash Water Tank, Rotating equipment's such as
Formation
Water Pumps, Dehydrator Charge Pumps, Sea-water Injection
Pumps, Sump
Pumps, and Chemical Injection Pumps.
High Pressure DGA (Diglycol Amine) at NGL Plant.
- Responsible in the detailed engineering design of
mechanical
equipment comprising of Chilled Water Surge Atmospheric Tanks;
Pressure
Vessels - Feed Gas Filter Separators, DGA Contactor, Rich DGA
HP Flash
Drum and Sweet Gas Separator. Heat Exchangers - Air Cooled
Feed Gas
Cooler, Shell and Tube Sweet-Sour Gas Exchanger, Sweet Gas
Chillers and
NGL/Chilled Water Exchangers. Rotating Equipment - DGA and
Chilled Water
Circulating Pumps and Sump Pumps.
Sulphur Forming Facility.
- Responsible in the detailed engineering design of the
mechanical
equipment which consist of Two Trains Rotoformer Units,
Exchangers,
Filters, Pumps, Vessels, Tanks, Conveyors.
Automated Gas Lift Facility.
- Responsible in the detailed engineering design of
mechanical
equipment consisting of Three 170 bar (2465 psi) turbine
driven gas-lift
compressors, a treatment plants, a gas dehydrator units using
a TEG
contactor and a regenerator, knock-out drums and gas coolers.
Dewpoint Control System/Propane Refrigerant System.
- Responsible in the detailed engineering design of the
mechanical
equipment comprising of Gas/Gas Exchanger, Gas Chiller, Propane
refrigerant Compressor, Low Temperature Separator, Propane Sub-
Coolers,
Hydrocarbon / Glycol Separator, Gas/Liquids Heat Exchanger,
Ethylene
Glycol (EG) Regeneration Package, EG Flash Tank, EG Lean/Rich
Exchanger
Coil, EG Reboiler/Still Column, EG Surge Tank with Heater, and
EG Pumps.
(OGP6): Projects undertaken with Fluor Daniel Arabia
Limited.
Mr. Garin's duties is to plan, develop, coordinates and
reviews the
technical work produced by the mechanical team. Interfaces with
clients,
project management and other engineering disciplines on critical
co-ordination and resolution activities. Estimates staffing
needs, develop
budgets and schedules, and assign work to the discipline.
Supervises the
daily work and activity of senior engineers, engineers and
designers
assigned to the discipline. Review and approved key design
documents
including drawings, calculations, technical specifications,
material
requisitions, bid evaluations and award recommendations; Prepares
Mechanical Punch Lists to ensure the readiness of systems for
release for
turn-over to the client or for start-up. Prepares work packages
and other
related information in a timely manner as required to support
the work
schedule. Participates in design reviews during all phases of
project and
discussions with other disciplines and the client.
Pipeline Gas Compression Station.
- Responsible in the mechanical engineering design and
project
management of a grassroot gas compressor station comprising of
two 1600
hp Compressors driven by Gas Turbines. The station design also
includes
inlet slugging facilities (slug catcher and filter separator),
gas/condensate separation, condensate stabilization system,
condensate
exportation, and a gas dehydration and dewpoint control.
Sales Gas Compression System.
- Responsible in the detailed engineering design of the
system. The
gas compressor suction pressure is 3447 kPag (500 psig). The
sales gas
is compressed to 7,585 kPag (1100 psig) using two single-stage
compressors in parallel. The two compressors are driven by
natural gas
fired 3.3 MW (4448 HP) Gas Turbines.
Pump Station with Condensate Storage.
- Responsible in the detailed engineering design of Two (2)
850 hp
horizontal split-case centrifugal pumps and a fixed roof
condensate
storage tank with a capacity of 1,500 cubic meters.
- Conducted a complete hydraulic analysis to determine pump
requirements, for the pipeline based on various operating
scenarios with
consideration given to the addition of future pumps.
Water Injection Facility.
- Responsible in the detailed engineering design of the
mechanical
equipment comprising of filtration deaeration system, a high-
pressure
chemical injection system and two 450 HP electically driven
high
pressure water injection pumps.
Chemical Injection Facility.
- Responsible in the detailed engineering design of
mechanical
equipment comprising of storage tank, distribution system and
injection
of chemicals to platform.
Community Services Center and Two S-5 Dhahran Warehouses.
- Responsible in the detailed engineering design of HVAC and
Refrigeration System, Fire Protection Systems. Demonstrated and
confirmed with client that the designed systems do meet the
prescribed
stringent requirement as called out in the client supplied
Specifications.
Maintain Potential 1982 To 1985 Increments.
- Responsible in the detailed engineering design of the
following:
ASME Section VIII Div 1 Pressure Vessels (Gas Scrubbers, Gas
Knock-Out
Drums and Slug Catchers); Scraper Traps (Launchers and
Receivers) to
ANSI B31.4; Fire Protection System to safe guard equipment's
and
structural members of the platform using the combination of
passive
system, fixed water spray system to NFPA 15 and 16
requirements and
oscillating foam/water monitors to NFPA 11 requirements.
Back to Table of
Contents.
|