______________________________________________
WING CONSTRUCTION
The kit arrived in July and I began to work on building wing
ribs. After only TWO MONTHS, I had the 52 ribs and 48 false ribs built. As I
lined up this stack of ribs as shown here, I was only a little nervous when I
had to trim the tails on my neighbors radial arm saw.

After completing the ribs, I started on
the spar construction. This basically involved building an "I" beam
for the main spar while constructing a much lighter rear spar. This picture
shows the full size blueprints while I finished up the first spar. Note the
crate in which the wing kit arrived mounted on the wall on the right side which
used to keep all of the ribs in alignment after I finish getting them in place

.
The ribs are slid onto the spar. Note the
angle iron.
After the ribs are installed the geodetic strips are glued into
place. Its during this process when the words "You can't have enough
clamps.... or troops in Madigascar" begin to make a lot of sense. In this
photo you can see the brackets for the interplane struts and the flying wires.
The nosepieces are glued into place and the leading edge plywood is added, then
scalloped. The aileron is then cut out and its leading edge is added.


By the end of 2000, I had the two bottom wings
finished, two more to go!
I finished the last two top wings, each taking about a month.
The learning curb really goes up quickly with this type of construction. Total
time on the four wings, about 325 hrs.
Starting in March 2001, I began the center section. This
required its own special oversized ribs. The auxiliary fuel tank fits inside of
this.

I then constructed the elevator, horizontal stabilizer and
rudder. Like the wingtip bows, these required me to laminate many pieces of
wood together. I would usually start by making a copy of the plan (so I can
still read the original) and laying it out on the workbench. Cover the
blueprint with plastic, drive nails around the perimeter and start slopping
T-88 everywhere. After using every clamp in sight, the part would start to take
shape and it’s off to the next step. Construction time for the tail feathers,
two months.
Introduction | Wing Construction | Fuselage
| Engine | Latest Photos | Other Builders and Flyers