Released by Project Control
Project Trak
OL2K INFRASTRUCTURE M1-PROJECT 
STATUS REPORT
DATE : 21-May-06
For the Week Ending 19-05-2006
 
                         
  DESCRIPTION WEEK CUMLATIVE  
  PLAN ACTUAL PLAN ACTUAL  
  Progress 1.57% 0.81% 7.12% 5.52%  
   
   
  Project Summary  
  CATEGORY SCOPE PLAN ACTUAL  
  CIVIL Concrete (Cu.M) 13350 2506 1527  
  STRUCT. STEEL (MT) 4318 369 650  
  PIPE Shop (Inch Dia) 76490 5172 5202  
  PIPE Erection (Inch Dia) 115112 - -  
  ELECT. Cable (Meter) 66764 - -  
  INSTR. Cable (Meter) 177557 - -  
                           
ACHIEVEMENTS                      
Structural Steel Erection 27 Tons 22-Apr-06
Concrete Pouring 70 Cu.M 1-May-06
CIVIL
PIPERACK FOUNDATIONS As on DATE : 20-May-06
SL. NO AREA TOTAL FDNS. UNIT EXCAVATION BLINDING FOOTING CONCRETE PEDESTALS CONCRETE BACK FILLING REMARKS
PLAN WFA ACT PLAN WFA ACT PLAN WFA ACT PLAN WFA ACT PLAN WFA ACT
1 PHASE 1A 46 No 46 46 46 46 46 46 46 46 46 46 46 46 46 46 46 COMPLETED
2 PHASE 1B 72 Cu.m 2705 5530 2725 17 28 21 15 21 9 9 9 6 7 6 6 Manual Excavation
3 PHASE 1C 48 Cu.m 2300 4646 1584   29 28   28 25   25         Manual Excavation
4 PHASE 2A 45 No 44 44 43 34 43 37 25 37 32 19 32 26 13 26 20 Contractor was instructed to give top priorty to 2A pedestals to enable structural works commencement - 1 Fdn. WFNA
5 PHASE 2B 52 No 52 38 36 52 36 31 52 31 30 52 30 30 52 30 26 WORK FRONT NOT AVAILABLE FURTHER
6 PHASE 3A 87 No 87 87 84 87 84 84 87 84 84 87 84 84 87 84 79 Work front not available for 3 Fdns.
7 PHASE 4A 63 No   42 36   36 36   36 36   36 14   14    Work front not available for 21 Fdns.
8 PHASE 5A 69 No                               IFC Drawings recd.  Work Front not available due to other contractot's interface
9 PHASE 5B 28 No                               IFC Drawings recd. Suvey to start
10 PHASE 6A 105 No 9                             IFC Drawings recd.  PERMIT yet to be obtained for Slit Trench works
11 PHASE 6B 234 No                                
12 PHASE 6C 213 No                                
  TOTAL (except Ph-1B & 1C)  1062 NO 239 257 245 236 302 283 225 283 262 213 262 206 205 206 177  
FOR PH - 1B & 1C 120 Cu.m 5005 10176 4309
STRUCTURAL  
  As on DATE : 20-May-06
SL NO PHASE TOTAL NO. OF PEDSTL. PADDING (NOS) PRE-ASSEMBLY (MT) ERECTION (MT) BOLT TIGHTENING (No of Columns) FINAL INSPECTION (No of Columns) PUNCH LIST JOBS (No of Columns) GROUTING (No of Columns) REMARKS
PLAN WFA ACT PLAN WFA ACT PLAN WFA ACT PLAN WFA ACT PLAN WFA ACT PLAN WFA ACT PLAN WFA ACT
1 1A 56 56 56 56 315 708 349 324 603 570 28 28 20 28 28 16 28 16   28 16    
2 1B 66                                            
3 1C 27                                            
4 2A 50                                            
5 2B 48                                            
6 3A 61 52 52 52 63 245 59 63 102 91 6 6                      
7 4A 65                                            
8 5A 58                                            
9 5B 12                                            
10 6A                                              
11 6B                                              
12 6C                                              
TOTAL 443 108 108 108 378 953 409 387 705 662 34 34 20 28 28 16 28 16   28 16    
PIPING
As on Date : 20-May-06
Sl. No Phase Ref Scope (ID) Fit-Up (ID) Welding (ID) Inspection (ID) Remarks
Plan WFA Actual Plan WFA Actual Plan WFA Actual
1 1A 8923 4,395.00 5,493.00 4,442.25 4,171.00 4,442.25 3,939.25 3,343.00 3,939.25 3,885.75  
2 1B 5585                    
3 1C 2749                    
4 2A 5839 1,468.00 2,256.75 548.75 1,404.00 548.75 442.00 853.00 442.00 68.00  
5 2B 7517                    
6 3A 5239   2,118.75 951.25   951.25 834.25   834.25    
7 4A 6581                    
8 5A 9316                    
9 5B 1111                    
10 6A 7217                    
11 6B 12313                    
12 6C 3150                    
  Total 75540 5,863.00 9,868.50 5,942.25 5,575.00 5,942.25 5,215.50 4,196.00 5,215.50 3,953.75