Name of Project & Location:
Laying of 8" Ø, 23,650 Rft, underground flow line from Duphri Remote facility to Mahi Remote facility & laying of 4" Ø, 3,100 Rft, underground flow line from Duphri-2 to Duphri Remote facility.Value of Work:
Rs. 10,956 MillionDate of Start:
March 26, 2004Date of Completion:
June 05, 2004Project Dexcription:
Laying of 8"Ø, 23,650 Rft and 4"Ø, 3,100 Rft, underground flow lines include- ROW preparation including dewatering, Hauling and stringing, Welding, Trenching/Excavation including dewatering, Holiday testing and coating repair, Lowering and backfilling, Hydrostatic testing including piggind and flushing, Installation of heat shrink sleeves on welded joint.
| - Sem Nala & road crossing (Thrust bore) | 1 No. |
| - Sem Nala & road crossing (Open ditch) | 1 No. |
| - Water course crossing (Thrust bore) | 1 No. |
| - Water course crossing (Open ditch) | 1 No. |
| - Pipeline anchor | 02 Nos. |
| - Pipeline marker post | 25 Nos. |
| - Concrete Cathodic Protection post | 12 Nos. |
| - Q.C. Inspection | L.S. |
| - As built drawing, ROW/Site clean up | L.S. |